Northline Metalworks sandbox demo · synthetic data

One relational source of truth, built from six spreadsheets. Every price runs through one engine.

Quote Q-2025-018 · priced by the engine

Boltless shelving unit 48x18x72, 5 shelf, qty 10

StationHoursLaborOverhead
Saw / Cut4.0$88.00$96.00
Brake / Form2.0$48.00$48.00
Weld6.0$168.00$168.00
Grind / Finish3.0$66.00$66.00
Powder Coat3.0$60.00$60.00
Assembly5.0$100.00$100.00
Material $1,974.00
Labor $530.00
Overhead $538.00
Subtotal $3,042.00
Markup 35%
Sell $4,106.70

Margins · every quote through the one engine

QuoteEst costSell MarginMargin %Flag
Q-2025-018$3,042.00$4,106.70$1,064.7025.9%
Q-2025-023$2,193.72$2,961.52$767.8025.9%
Q-2025-031$581.98$750.00$168.0222.4%hand-set, -35.67 vs engine

Estimate vs actual · Q-2025-018 (from the production log)

StationEst hrsAct hrs Delta
Saw / Cut4.04.2+0.2
Brake / Form2.02.0+0.0
Weld6.08.0+2.0overrun
Grind / Finish3.03.5+0.5
Powder Coat3.03.0+0.0
Assembly5.05.2+0.2
Cost est $3,042.00
Cost actual $3,294.20
Margin est $1,064.70
Margin actual $812.50
The quote looked fine. Welding ran over, so the real margin on this job was $812.50, not $1,064.70. Before, nobody could see that.